Oil & Gas Permitting Requirements Well Pad Special Use/Building Permits (SU/BP)
Pursuant to Article 9 of the Rio Blanco County Land Use Regulations, oil and gas drilling activities within unincorporated Rio Blanco County require an approved Well Pad Special Use/Building Permit (SU/BP).A separate SU/BP is required for each new well pad. Completed applications must be submitted to the Rio Blanco County Community Development Department no later than 30 days before the anticipated construction of the well pad or access road.
An approved permit may include multiple wells on the same pad, associated facilities, and reclamation activities. Construction may not begin until the required permit has been approved and issued.
Well Pad SUBP Application
Pipeline Special Use/Building Permits (SU/BP)
Pursuant to Article 9, Section 9-301, pipelines located outside an approved Well Pad SU/BP require a Pipeline Special Use/Building Permit unless otherwise included under an approved well pad application.Pipelines directly connecting wells to collection systems may be included with a Well Pad SU/BP when they are no more than 5 miles in length and submitted concurrently with the well pad application. All other applicable off-pad pipelines require a separate Pipeline SU/BP.
Applicants must provide documentation of compliance with applicable ECMC requirements. Upon completion, an as-built map identifying the pipeline location must be submitted to the County Building Division for recording. The location of abandoned pipelines must also be submitted to the County.
Pipeline applications are reviewed according to the applicable Administrative, Limited Impact, or Major Impact review requirements established in Article 9.
Pipeline Special Use/Building Permit Application
Temporary Living Quarters (TLQs)
Temporary Living Quarters are regulated under Article 8 of the Rio Blanco County Land Use Regulations. The applicable review and permit requirements are determined by the number of workers accommodated, the location of the quarters, and the type of structures proposed.The three TLQ classifications are:
- Type 1: Fewer than 25 workers, located at the worksite or well pad.
- Type 2: Up to 50 workers, located away from the worksite or well pad.
- Type 3: More than 50 workers, located away from the worksite or well pad, with permanent structures.
Type 1 TLQs located on a well pad may be included under the Well Pad SU/BP, subject to applicable Administrative Review requirements. Other TLQ proposals are subject to the separate review and permitting requirements established in Article 8.
Where required, a County building permit and Certificate of Occupancy must be obtained before occupancy. Permit expiration, extensions, removal of temporary structures, and reclamation must comply with Article 8.